The rapid expansion of AI and data center capacity is set to add over 10,000 TWh to electricity demand in the next decade, prompting utilities worldwide to plan massive grid investments.

Global electricity demand is projected to rise by more than 10,000 TWh over the next ten years as the information technology sector, especially AI-driven data centers, expands. The International Energy Agency warned in its World Energy Outlook that the surge in data-center power use is straining supply chains and raising concerns about keeping electricity affordable.

The agency emphasized that "successful electrification means keeping electricity available and affordable, putting the emphasis on effective use and expansion of grids, and greater operational flexibility in power systems," while noting that AI’s current impact is to amplify grid stresses.

A Cornell University study found that data-center operators in four U.S. regions covered only 38% of the costs for grid connections, paying $3.12 billion, while households absorbed the remaining $5.13 billion.

In the United States, the Wall Street Journal reported about 58 GW of new data-center capacity under construction across 577 sites, a demand comparable to six times the peak electricity use of New York City. One-fifth of this new capacity is slated for Texas, where Governor-elect Gina Hinojosa’s campaign called for a moratorium on data-center approvals until legislators can establish protections for local communities, echoing a similar ban earlier this year by Governor Greg Abbott.

Europe’s net-zero agenda includes a planned overhaul of the regional grid, with the European Commission proposing to double cross-border interconnectors at a cost of 584 billion euros (about $641 billion) by 2030, a sum expected to be funded largely by consumers.

Analysts note that the scale of required grid upgrades creates a tension between the goal of affordable electricity and the financing burden on utilities and governments, highlighting the need for data-center operators to assume a larger share of infrastructure costs.