ICA officer leads legal and operational groundwork for Singapore-Malaysia RTS Link

Ամփոփում

Superintendent Serene Lim Kah Ghee of Singapore's Immigration & Checkpoints Authority has overseen the legal framework, bilateral agreements and operational planning that will enable the five-minute cross-border rail service to open in February 2027.

Singapore’s Immigration & Checkpoints Authority (ICA) has completed the legal and operational preparations for the Johor Bahru-Singapore Rapid Transit System (RTS) Link, which is slated to begin service in February 2027. The cross-border rail will connect Woodlands North station in Singapore with Bukit Chagar station in Johor Bahru, allowing passengers to travel the five-minute journey after clearing immigration once before boarding.

Superintendent Serene Lim Kah Ghee, who serves as Deputy Commander (Operations) and Senior Assistant Director (Rail & Air Development) at ICA, has coordinated the project’s planning, management and review. Her responsibilities include working with the Home Team Science and Technology Agency, Land Transport Authority, Changi Airport Group, RTS Operations Pte Ltd and Malaysia’s Border Control and Protection Agency to develop joint standard operating procedures, monitor station fit-out works and ensure ICA’s operational requirements are met.

Lim helped draft the Cross-Border Railways (Border Control Co-location) Bill, which was passed in May 2026 to provide the domestic legal basis for co-located customs, immigration and quarantine facilities at both stations. The legislation clarifies the powers, responsibilities and legal immunity of ICA officers operating in Malaysia, enabling Singapore’s immigration clearance to be performed on the Malaysian side of the link.

A joint field-training exercise on 27 October brought together agencies from both countries to test incident-management protocols, including a simulated fire on an RTS train. Lim said the exercise demonstrated that the negotiated legal framework and operational procedures could work in practice.

RTS Operations Pte Ltd expects system tests and trial runs to be completed by 31 December 2026 and expressed confidence that the line will be ready for service in February 2027. Lim noted that the rail link will provide a predictable alternative to road travel across the Causeway, potentially reshaping daily commuting patterns for work and leisure.

Lim, who received the Public Administration (Bronze) Medal at the 2026 National Day Awards, said the project underscores the importance of trust and partnership between Singapore and Malaysia and hopes commuters will appreciate the extensive bilateral effort behind the short ride.