Victorian transport minister delayed level crossing works ahead of 2022 election, adding $16.5 million to project cost
Gauche

Victorian transport minister delayed level crossing works ahead of 2022 election, adding $16.5 million to project cost

Résumé

Freedom-of-information documents show that former transport infrastructure minister Jacinta Allan ordered the Glen Huntly level-crossing removal to be rescheduled to keep Frankston express trains running before the November 2022 state election, resulting in an extra $16.5 million expense for taxpayers.

Freedom-of-information documents obtained by The Age reveal that Jacinta Allan, then transport infrastructure minister, instructed contractors on the Glen Huntly station level-crossing removal to postpone planned track closures until December 2022. The change was made to maintain express services on the Frankston line ahead of the November 2022 state election, according to briefing papers.

The rescheduling required night and weekend shifts, overtime rates and additional residential relocations, increasing the project’s cost by $16.5 million beyond the original estimate of $22-$28 million. An advisory note warned that about 1,600 nearby residences might need relocation during the accelerated work period in 2023.

Opposition MP James Newbury criticised the decision, saying it was taken to avoid voter backlash and that it “cost taxpayers millions.” A spokesperson for Allan responded that the adjustment followed a recommendation from the Victorian Infrastructure Delivery Authority to minimise passenger disruption while keeping the overall project on schedule.

The contractor, the Southern Program Alliance, accelerated construction after the election through intensive night shifts and extra weekend work. An independent estimator later confirmed that the additional overtime, traffic-management changes and residential relocations accounted for the extra spending, which was added directly to the public bill for the project.

The documents also note that similar political considerations have influenced rail-work scheduling in previous Victorian elections, with express-service shutdowns avoided in the weeks leading up to polls.