Victorian transport minister delayed level crossing works ahead of 2022 election, adding $16.5 million to project cost
Left

Victorian transport minister delayed level crossing works before 2022 election, adding $16.5 million to project cost

Select a version of the text written from a presumed ideological perspective. This is not the original text, but a hypothetical version — how someone with that viewpoint might have phrased it. Tapping the current version again will return to the original or select cleaned version.

Summary

Freedom-of-information documents show that then transport infrastructure minister Jacinta Allan ordered the Glen Huntly level-crossing removal to be pushed back so Frankston express trains could keep running before the November 2022 state election, leaving taxpayers to absorb an extra $16.5 million.

Freedom-of-information documents obtained by The Age reveal that Jacinta Allan, then transport infrastructure minister, directed contractors on the Glen Huntly station level-crossing removal to delay planned track closures until December 2022. The move was made to preserve express services on the Frankston line ahead of the November 2022 state election, according to briefing papers, putting election convenience ahead of straightforward project planning.

That rescheduling demanded night and weekend shifts, overtime rates and extra residential relocations, driving the project’s cost up by $16.5 million beyond the original estimate of $22-$28 million. An advisory note warned that about 1,600 nearby residences might need relocation during the accelerated work period in 2023, underscoring how the politically timed delay complicated the job and added pressure on locals.

Opposition MP James Newbury condemned the decision, saying it was taken to avoid voter backlash and that it “cost taxpayers millions.” A spokesperson for Allan said the adjustment followed a recommendation from the Victorian Infrastructure Delivery Authority to minimise passenger disruption while keeping the overall project on schedule, but the documents show the scheduling choice still shifted substantial costs onto the public.

The contractor, the Southern Program Alliance, accelerated construction after the election through intensive night shifts and extra weekend work. An independent estimator later confirmed that the additional overtime, traffic-management changes and residential relocations accounted for the extra spending, which was added directly to the public bill for the project.

The documents also note that similar political considerations have influenced rail-work scheduling in previous Victorian elections, with express-service shutdowns avoided in the weeks leading up to polls.