Melbourne officials once proposed a 20-storey airport rail station linking the Suburban Rail Loop and Airport Rail Link

Résumé

A 2019 plan to stack a Suburban Rail Loop station atop a new Airport Rail Link station at Melbourne Airport was abandoned after internal criticism, and the project’s design and cost estimates are now under scrutiny by a royal commission.

In late 2019, Rail Projects Victoria chief executive Evan Tattersall presented a proposal to combine Victoria’s Suburban Rail Loop (SRL) with the Melbourne Airport Rail Link (MARL) by constructing a 20-storey, double-deck station above the airport’s air-traffic control tower. The concept would have placed SRL passengers at roughly the same height as air-traffic controllers, a design described by an attendee as “insane.”

The idea emerged while the Andrews government was evaluating the privately-backed AirRail Melbourne proposal, which promised a faster, underground airport connection. Government officials favored an above-ground solution and considered placing the SRL station on top of the MARL structure. The plan was later dropped, and Tattersall declined to comment.

Since then, the alignment of the northern SRL segment with the MARL remains unresolved. Premier Ben Carroll has called the airport link his “highest priority,” and Opposition leader Jess Wilson has also pledged support. Allegations revealed in a royal-commission submission claim that the MARL business case relied on inaccurate cost figures and that a public-service executive was threatened to secure a politically preferred route. Minister Jacinta Allan, who oversaw the project at the time, has denied the accusations.

The government’s later decision to route airport trains through the Metro Tunnel rather than a dedicated Sunshine tunnel altered the project’s scope. The original AirRail estimate of an 18-minute journey from Southern Cross to the airport was replaced with a forecast of 29 minutes, with some analysts suggesting the actual travel time could approach 40 minutes once additional stops are included. A source familiar with the project warned that longer travel times could reduce patronage, making alternative modes such as ride-share or SkyBus more attractive.

The shift also means airport services will share capacity with suburban trains in the Metro Tunnel, which is projected to reach full utilisation by 2031. Critics argue this will limit the frequency of airport trains and increase congestion on western suburban lines.

Cost estimates for the MARL have varied, with a 2021 figure of $11.5 billion and a combined state-federal pledge of $12 billion that includes funding for signalling, grade separations at Sunshine station, and a new station at Keilor East. The first airport train is now expected to run in 2031.

The royal commission, which will hold its first public hearing on Monday, is set to examine the project’s financial and planning decisions, including the dismissal of the AirRail proposal and the abandonment of the Sunshine tunnel concept.

Source

The Age

Continuez à lire — gratuitement

Créez un compte gratuit pour suivre l'actualité. Aucune carte requise.