Inspection finds 85 coating failures in Lincoln Memorial Reflecting Pool after rushed renovation
Version nettoyée

Inspection finds 85 coating failures in Lincoln Memorial Reflecting Pool after rushed renovation

Résumé

A contractor-commissioned inspection identified 85 defects in the Reflecting Pool's blue coating, attributing the problems to premature refilling and material issues rather than vandalism.

An inspection report commissioned by Atlantic Industrial Coatings (AIC) documented at least 85 failures in the blue coating applied to the Lincoln Memorial Reflecting Pool this summer. The report, dated Aug. 6, said the defects—including blisters, peeling and cracks—resulted from errors such as refilling the basin before the liner had fully cured, use of improper materials and rushed work to meet the "America 250" anniversary timeline.

The 75-page analysis, prepared by Atlantic Coating Inspection, includes photographs of the damaged areas and cites likely causes such as insufficient drying time, misapplication of primer and inadequate flexibility of the coating over expansion joints. Workers were still applying the coating the day before the pool was refilled on June 4, despite a required 72-hour cure period.

AIC, which completed the $14.7 million renovation under a no-bid contract awarded by the Trump administration, described most of the failures as "cosmetic" but acknowledged some were "systemic." The contractor offered a repair plan but did not include cost estimates, stating the work would be covered under warranty.

An Interior Department spokesperson said AIC is contractually obligated to fix the Reflecting Pool and is "well on its way to doing so," promising that the work will be "perfect" and that sections damaged by vandals will be replaced. White House spokesperson Taylor Rodgers called the repairs an example of President Trump restoring the nation's capital.

Earlier, President Trump and senior officials had blamed vandals for the pool's problems, and federal prosecutors had charged four individuals, including former Olympic canoeist David Hearn, with damaging the liner. Those charges were later dismissed after evidence pointed to contractor error.

The inspection also noted 88 additional instances of damage caused by the Army Corps of Engineers during testing, and 12 cuts that reached the concrete. Recommendations from the report emphasize adhering to curing time guidelines and testing coating products before application.

AIC plans to modify its repair approach by avoiding the use of the dark blue Pipeliner 5000 over expansion joints, employing a more flexible material, and using a different primer as advised by the coating manufacturer. The contractor warned that the warranty could be voided if water contacts the repaired surface within 24 hours or the perimeter caulking within seven days.

President Trump later said the upcoming fixes would make the pool "as vandal-proof as you can get."